Quick Answer: The Blueprint Intergovernmental Agency is the joint Tallahassee-Leon County agency that spends the local one-cent sales tax on infrastructure and economic development through 2039. In 2026 its board adopted the FY2027 operating budget and five-year capital program and offered $81.8 million in new sales tax bonds for the gateway roads and the Fairgrounds. Cost estimates on the three largest road projects have risen by about $100 million, and that increase is now driving decisions about which projects get built and when.
Leon County’s one-cent sales surtax pays for the largest local road, park and stormwater building program in the Tallahassee region. The Leon County-City of Tallahassee Blueprint Intergovernmental Agency spends that money. Its board is made up of all seven Leon County commissioners and all five Tallahassee city commissioners. In 2026 the agency has borrowed more, adopted a new budget, and argued in public over rising project costs. Contractors, landowners, developers and employers across Tallahassee and nearby Gadsden, Wakulla and Jefferson counties have a stake in the result.
What is Blueprint and how is it funded?
Blueprint runs on the one-cent local infrastructure sales surtax. Leon County voters approved the current extension on November 4, 2014, and it runs through December 31, 2039. The 2026 bond disclosure says the extension pays for projects to improve roads, reduce traffic congestion, protect lakes and water quality, and reduce flooding, among other purposes. The extension also created a dedicated economic development program. The agency’s Office of Economic Vitality (OEV) was formed in 2016 to support a stronger Tallahassee-Leon County economy.
Blueprint’s bonds are backed by 78 percent of the one-cent surtax, plus certain funds and investment earnings. The bonds are not general obligations of the city or county, and the agency has no power to levy taxes.
| Blueprint at a glance | Detail |
|---|---|
| Governing board | Leon County and City of Tallahassee commissioners |
| Funding source | One-cent local infrastructure sales surtax |
| Surtax expires | December 31, 2039 |
| Share pledged to bonds | 78% of surtax proceeds |
| Economic development arm | Office of Economic Vitality (formed 2016) |
| Director | Autumn Calder |
| Net position (9/30/2025) | $298.7 million |
How much sales tax revenue does Blueprint collect?
Revenue grew strongly after the pandemic and then leveled off. The preliminary official statement for the agency’s May 2026 bond sale lists total infrastructure surtax collections, and the 78 percent share pledged to bonds, for each fiscal year ending September 30:
| Fiscal year | Total surtax | 78% pledged share |
|---|---|---|
| FY2019 | $46.8 million | $37.4 million |
| FY2020 | $42.8 million | $34.3 million |
| FY2021 | $51.0 million | $39.8 million |
| FY2022 | $60.3 million | $47.0 million |
| FY2023 | $60.8 million | $47.4 million |
| FY2024 | $63.0 million | $49.2 million |
| FY2025 (unaudited) | $61.3 million | $47.8 million |
Collections fell from about $46.8 million in FY2019 to $42.8 million in FY2020. They then rose about 47 percent to a peak of $63.0 million in FY2024. The bond disclosure gives an unaudited FY2025 total of $61.3 million. It also cites HB 7031, the state law that ended sales surtax collections on commercial leases effective October 1, 2025. That change removes commercial rent from the surtax base from FY2026 on.
Blueprint’s audited financial statements for the year ended September 30, 2025 report $50.7 million in shared revenues, up from $49.2 million a year earlier. They report total government-wide revenues of $63.9 million. Fund-level spending reached $82.2 million, including $36.9 million in capital outlays. As a result, the combined fund balance fell by $6.9 million to $305.5 million. Of that balance, $292.5 million is restricted for infrastructure. The economic development expense line was $5.3 million in FY2025, down from $19.1 million in FY2024.
What is in Blueprint’s FY2027 budget?
The board held its FY2027 budget workshop in June 2026. WTXL ABC 27 reported that the board approved a $70 million operating budget for the next fiscal year, with final adoption to follow after two public hearings. According to a Govly summary of the workshop, the budget included $31.4 million for infrastructure projects, including the Cascades Trail and regional mobility work. It also included $4.6 million for OEV business development and workforce programs. The staff-recommended balanced budget passed on a roll call vote. Some members opposed it over project funding and priorities.
Leon County Commissioner David O’Keefe again declined to support the budget. He asked for full transparency on cost estimates for every project and for the board to regain budgeting authority over individual projects.
The board held the final public hearing in September 2026. There it adopted the FY2027 operating budget and the five-year capital improvement program. At the same meeting, board members unanimously directed staff to begin a substantial amendment process to reprioritize projects. Members also directed OEV to work with local chambers, universities and other partners on a one-page economic development strategy.
How much is Blueprint borrowing in 2026?
On May 14, 2026, the agency released a preliminary official statement for $81.81 million in Sales Tax Revenue Bonds, Series 2026, with bids due May 27. The proceeds are for the Airport Gateway, Northeast Gateway, Northeast Connector Corridor, Northwest Connector Corridor, North Monroe Gateway, and Fairgrounds Beautification and Improvements. Fitch Ratings assigned an AA rating and Moody’s assigned Aa2, both with stable outlooks. Principal payments are scheduled every October 1 from 2027 through 2039, the year the surtax ends. The largest payments come at the end: $12.9 million in 2038 and $14.2 million in 2039.
The disclosure shows maximum annual debt service on parity bonds of $33.5 million. Estimated coverage from pledged sales tax revenue is 1.43 times for FY2025 and 1.47 times for FY2024. The bond resolution allows additional parity bonds only if pledged revenue covers maximum annual debt service at least 1.25 times. The disclosure also says projects under construction are expected to cost $659.6 million.
| Debt outstanding (9/30/2025) | Principal | Rate / final payment |
|---|---|---|
| Series 2024 Bonds | $116.0 million | 5.0%-6.0% / Oct. 2038 |
| Series 2022 Bonds | $68.2 million | 4.0%-5.0% / Oct. 2038 |
| State Infrastructure Bank loan | $21.0 million | 1.85% |
| Regions Bank note | $7.1 million | 1.78% / Oct. 2035 |
| Total | $212.3 million | Before Series 2026 |
In March 2024, the board approved $136 million in bond financing for projects including the Northeast Gateway and the Bannerman Road widening. If the full Series 2026 amount is issued, Blueprint’s total borrowing will approach $300 million, all of it to be repaid from sales tax by 2039.
Where do Blueprint’s major projects stand?
In December 2025, Director Autumn Calder said 16 Blueprint projects would be under construction in 2026. She said those projects would deliver 26 miles of roadway improvements, 119 miles of bicycle and pedestrian improvements, 52 miles of greenways and 337 acres of parks.
What is the status of the Northeast Gateway?
The Northeast Gateway builds Welaunee Boulevard in northeast Tallahassee. Its purpose is to improve regional mobility and take pressure off US 319, US 90 and two canopy roads. By late 2025, construction was visible from Interstate 10 and early work had begun on the overpass bridge. Sidewalks, stormwater ponds and a multi-use path were scheduled for completion by November 2026, with the bridge due by summer 2027. At the end of FY2025, the audit carried $64.0 million in land and construction in progress for the project, up from $38.5 million a year earlier.
What is happening with Bannerman Road?
The Northeast Corridor Connector widens Bannerman Road from Thomasville Road to Preservation Road. It also adds multimodal and stormwater improvements and extends greenways. In December 2025 the project was in land acquisition. A new sidewalk on Bull Headley Road was finished, a turn lane at the Bannerman intersection was planned for 2026, and major road work was set to begin in 2027. The audit recorded $19.2 million in land and construction in progress at September 30, 2025.
Is the Airport Gateway still moving forward?
The Airport Gateway is meant to create a multimodal entrance from Tallahassee International Airport to downtown, Florida State University and FAMU. The 2026 bond disclosure describes more than 7 miles of roadway improvements and about 12 miles of new sidewalks, bike lanes and multi-use trails. The project has been disputed for years. In 2023, its estimated cost rose from $82 million to about $123 million, and Commissioner Christian Caban asked the board to improve existing roads instead. FSU had contributed $3 million to the project. In May 2024 the project stayed in the budget because there was not a supermajority to change its scope. At the September 2026 meeting, members discussed moving funds away from Segment C, a new road of more than a mile from West Orange Avenue to Levy Avenue. According to the meeting summary, Segment C is unlikely to proceed because it lacks state approval and conflicts with FSU land use plans. The substantial amendment process will confirm its status.
What about Orange-Meridian and the Fairgrounds?
The Orange-Meridian Placemaking project broke ground on May 8, 2025. It is a neighborhood park near the southwest corner of Orange Avenue and Meridian Street. Plans include shaded play and fitness areas, picnic pavilions, a trail, and improvements to the East Drainage Ditch for stormwater management. Blueprint funds the park with support from a Resilient Florida grant, and the city will maintain it.
Blueprint approved $30 million for Fairgrounds Beautification and Improvements in 2024, and the project is part of the 2026 bond plan. The county owns the roughly 107-acre property on South Monroe Street. The North Florida Fair Association leases it for $1 a year through 2067. In February 2026 the Blueprint board directed staff to renegotiate the lease to give the county more control over about 50 acres planned for mixed-use development. The association rejected most county terms in a March 27 letter and asked for ownership of about 60 acres instead. On April 14, 2026, the County Commission named Chair Christian Caban as its negotiator. A 2021 feasibility study estimated about $79 million in annual visitor spending tied to the fairgrounds.
Why are Blueprint project costs rising?
Records compiled by Commissioner O’Keefe show that costs for the three gateway projects receiving most of the funding have risen by about $100 million from their initial estimates. Those projects are the Northeast Gateway, the Airport Gateway and the Northeast Corridor Connector. WTXL reported that estimates for Bannerman Road and the Northeast Gateway alone rose by at least $60 million between September 2024 and May 2025. Calder has attributed the increases to inflation, unforeseen conditions and design updates. She said prices could still move with labor, tariffs, material supply and contractor availability. O’Keefe has warned that rising costs could leave other projects, such as Tharpe Street, without money.
What does the Office of Economic Vitality fund?
OEV runs Blueprint’s business programs, including the Competitive Project Fund and the Future Opportunity Leveraging Fund. In June 2026, the board unanimously approved $375,000 for Neighborhood Medical Center, a federally qualified health center, to add an on-site pharmacy. OEV projected nearly $3.9 million in economic output, 11 jobs and about $1.5 million in wages and income from the project. OEV also tracks more than 80 metrics in a quarterly economic dashboard. It promotes the LEAP Community Bootcamp, which FSU’s Jim Moran Institute for Global Entrepreneurship runs for residents of Leon, Gadsden and Wakulla counties.
What does Blueprint mean for local business?
For contractors and suppliers, Blueprint is one of the region’s largest steady sources of public work. The agency spent $36.9 million on capital outlays in FY2025. It has $659.6 million in projects under construction and is borrowing further to keep them going. That pipeline matters to site-work, paving and stormwater firms across the Big Bend, including those based in Gadsden, Wakulla and Jefferson counties. For developers and landowners, the gateway roads open land in northeast Tallahassee and near the airport. Any change to the Airport Gateway, or a lease agreement on the Fairgrounds, would change which land is likely to be developed.
There are also risks. Surtax revenue has flattened, commercial rent no longer adds to the base, and debt service now uses most of the 78 percent pledged share. Higher project costs leave less flexibility for projects that have not started. The substantial amendment process the board launched in September 2026 is where those trade-offs will be decided.
Frequently Asked Questions
When does the Blueprint sales tax expire?
The one-cent surtax extension approved by Leon County voters on November 4, 2014 runs through December 31, 2039. All of Blueprint’s current bonds are scheduled to be repaid before that date.
How much sales tax did Blueprint collect in FY2025?
The May 2026 bond disclosure lists unaudited FY2025 surtax collections of $61.3 million, with $47.8 million in the 78 percent pledged share. Collections peaked at $63.0 million in FY2024.
How large is Blueprint’s FY2027 budget?
WTXL reported a $70 million operating budget approved at the June 2026 workshop. The board adopted the final operating budget and five-year capital improvement program after the September 2026 public hearing.
Is the Airport Gateway canceled?
No. The project is in the 2026 bond plan. Board members have discussed moving money away from Segment C, the new road between West Orange Avenue and Levy Avenue, and that segment’s status will be settled through a substantial amendment process.
Sources and Further Reading
- Preliminary Official Statement, Sales Tax Revenue Bonds, Series 2026, Leon County-City of Tallahassee Blueprint Intergovernmental Agency
- Summary Notice of Sale, Blueprint Intergovernmental Agency Sales Tax Revenue Bonds, Series 2026, The Bond Buyer
- Blueprint Intergovernmental Agency Annual Financial Report, Fiscal Year 2025, Florida Auditor General
- Blueprint project costs spark transparency calls from commissioner, neighbors, WTXL ABC 27
- 16 Blueprint projects to be under construction in 2026, WTXL ABC 27
- Blueprint approves $136M in bond financing for multiple projects, WTXL ABC 27
- Blueprint Intergovernmental Agency Budget Workshop and Board of Directors meeting summaries, June and September 2026, Govly
- Blueprint: Budget Approved, Airport Gateway Stays, Affordable Housing Project Voted Down, Tallahassee Reports
- Commissioner Caban to Negotiate Fairground Lease, Tallahassee Reports
- Christian Caban asks Blueprint to reconsider new Airport Gateway road, Tallahassee Democrat
- Orange-Meridian Placemaking groundbreaking announcement, City of Tallahassee
- Strategic OEV Investment Advances newsletter, Tallahassee-Leon County Office of Economic Vitality